Sourcing a Critical Part for Smurfit Westrock in Yakima
Last updated: October 27, 2026
Executive Summary
By 6:30 that evening, Phil had worked the vendor's after hours line and coordinated with Westrock's freight forwarder to set up an early morning pickup. The 80-pound pallet left New Jersey the next morning and was scheduled to reach Yakima at approximately 1:30 a.m. on September 4, less than 34 hours after Westrock's first call.
Quick Review: Motors & Controls sourced a Siemens HNF664J heavy-duty disconnect — a part and brand MCC does not carry — finding the only available unit in the U.S. within 15 minutes and scheduling the part to arrive in less than 34 hours, versus a 14-week lead time elsewhere.
Project type: Emergency sourcing and expedited freight coordination for a non-stocked electrical component
Industry: Corrugated Packaging / Manufacturing
Scope: Locate, quote, purchase, and ship a Siemens 200 amp, 600 volt non-fused heavy-duty safety switch from New Jersey to Yakima, working with the customer’s freight forwarder
Role: Motors & Controls located the part, quoted it within 15 minutes, arranged the vendor’s after-hours pickup, and coordinated freight with CAP Logistics, keeping the customer updated at every step.
Project Background
Westrock has been an MCC customer since 2014, and sales to the Yakima facility have grown steadily over the past three years. The account is supported by MCC outside sales representative Jenny Colgan and by Phil Lizee, an inside sales representative at MCC since 1996. When Westrock Maintenance Coordinator Kim West needed help that afternoon, MCC was one of her first calls.
The Challenge
Local stock did not exist. Some national online distributors listed the switch as in stock, but its listing carried a 14-week lead time. Time of day mattered. With less than an hour of the business day left in the Pacific Northwest, it was already 6:45 p.m. on the East Coast, and most suppliers there had closed for the day.
Implementation
Westrock uses CAP Logistics as its freight forwarder, and the plan was for CAP to pick up the part early the next morning and get it moving west the same day. Once Kim approved the purchase, Phil reached the vendor through its after-hours line and arranged an 8:30 a.m. Eastern pickup. He then walked through CAP's pickup options with Kim, and the plan was finalized at 6:30 p.m. At 7:00 p.m., Phil emailed Kim the order confirmation, the vendor's confirmation, and a status update.
Phil did not wait for start of business to tell him whether the plan held. At 6:00 a.m. Pacific, on his way into work, he called the vendor to confirm the pickup was set. He dialed the number from memory. Phil has a near-photographic memory for numbers. By 6:15 a.m. he had left Kim a voicemail confirming everything was on track, and he texted Jenny Colgan so she could update everyone involved at Westrock.
By 8:00 a.m. Pacific, CAP Logistics had picked up the 80-pound pallet in New Jersey. From there, the part had to cross the country. CAP could not secure a flight into Yakima's small regional airport, and the shipment was scheduled to arrive at the plant at approximately 1:30 a.m. on September 4.
Results
Kim and the Westrock team were kept informed at every step, through a written confirmation that evening, a voicemail before 6:30 the next morning, and updates to the wider team through Jenny Colgan.
Conclusion
For Smurfit Westrock, the difference was experience. Phil Lizee brought 30 years of inside sales knowledge to a part MCC had never carried, and he followed it through from the first call to the morning pickup. That is what a 12-year customer relationship looks like when it is tested.